Answer:
0.726 is the probability that the project will be completed in 33 days or less.
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 30 days
Variance = 25 days
Standard Deviation,

We assume that the distribution of path length is a bell shaped distribution that is a normal distribution.
Formula:

P(completed in 33 days or less)
Calculation the value from standard normal z table, we have,

0.726 is the probability that the project will be completed in 33 days or less.
Answer:
£151.20
Step-by-step explanation:
20%= 100%divided by 5
To find 100% from 20% you x by 5
so you times 30.24 by 5
30.24x 5 = 151.2
So the answer is £151.20
interest percentage rate would be 1.6754%
Answer:
B
Step-by-step explanation:
when you solve B you get 15 and for all the other ones you get a non-terminating decimal
I have added a screenshot with the complete question along with a diagram representing the scenario.
<u><em>Answer:</em></u>s = 22°
<u><em>Explanation:</em></u><u>1- getting the top right angle of line B:</u>We are given that:
the top right angle of line A = 158°
Since lines A and B are parallel, therefore, the top right angle of line A and the top right angle of line B are corresponding angles which means that they are equal
This means that:
<u>Top right angle of line B = 158°</u>
<u>2- getting the value of s:</u>Now, taking a look at line B, we can note that:
angle s and the top right angle form a straight angle. This means that the sum of these two angles is 180°
Therefore:
180 = s + 158
s = 180 - 158
<u>s = 22°</u>
Hope this helps :)