<span>The 4 in the hundreds place has a value400 tines as great as the 0 in the ones place.</span>
Answer: the due date would be 92 weeks
Step-by-step explanation:
Since the time required to complete a project is normally distributed, we would apply the formula for normal distribution which is expressed as
z = (x - µ)/σ
Where
x = number of weeks.
µ = mean
σ = standard deviation
From the information given,
µ = 80 weeks
σ = 10 weeks
If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, the z score corresponding to 90%(90/100 = 0.9) is 1.29
Therefore,
1.29 = (x - 80)/10
x - 80 = 1.2 × 10
x - 80 = 12
x = 80 + 12 = 92
Answer:
0
Step-by-step explanation:
To solve this, you first plug in the 4 and 2 where the x and y's go, making the expression (4 - 2(2))*(4 + 2(2)). Then you solve each parenthesis (below).
(4 - 2(2))*(4 + 2(2)).
(4 - 4)*(4 + 4).
0*8
0
Hope this helped! If you have any questions, feel free to message me :)
Its simple really. If say a person bought a sandwich for $5.00, and the tax was 7%. You would have to multiply the amount of the sandwich to 0.07. Doing this would tell you how much the tax is. Then you would simply add them to get your total. This also applies with tip, markup, and discount.