Answer: contingency
Explanation:
Contingency planning is a form of planning that is used by an organization in order to plan ahead in case an event occurs. Contingency plans can also be called a 'Plan B' due to the fact that it's an alternative action in case things does not go as planned.
Therefore, based on the question, Pinnacle is practicing contingency planning.
% return would be (total profit / total invested) * 100 so
( 100 / 1000 ) * 100 = 10%
Answer:
True
Explanation:
An activity based costing (ABC) system assigns resources to the different production activities, and then unit costs are determined by the proportion of the production activities that every unit requires.
This is a much more complex costing method than just assigning overhead costs based on direct labor hours or machine hours.