Each side is about 290mm long
Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Let
x------> the number of multiple choice question
y------> the number of free response question
we know that
-----> equation A
-----> equation B
Substitute equation B in equation A
Find the value of x
therefore
<u>the answer is</u>
the number of multiple choice question are
the number of free response question are
Answer:
B. G(x) = x³ - 5
Step-by-step explanation:
The graphs below are the same shape. They share the same formula but different y-intercepts.
F(x) = x³ has a y-intercept of 0.
F(x) = x³ + 0
G(x) has a y-intercept of -5.
G(x) = x³ - 5
Answer:
Step-by-step explanation:3,9,27,81 because this is multiplication