Answer: False
Explanation:
The Fair Labor Standards Act enacted into law in 1938, covers the protection of employees' rights such as minimum wage, child labor laws and overtime conditions.
According to the Fair Labor Standards Act, an employee who works overtime is entitled to a payment of one and half times their hourly pay. However overtime counts as working for more than 40 hours in a week.
Because Sally has only worked for 37 and a half hours, she will not be entitled to any overtime pay.
Answer:
Schrock record the $65,920 as the cost of the new van
Explanation:
The computation of cost of the new van is computed below:
= Purchase cost + sales tax + logo cost + safety testing cost
= $60,000 + $4,500 + $1,200 + $220
= $65,920
where,
Purchase cost is $60,000
Sales tax is $4,500
Logo cost is $1,200
Safety testing cost is $220
The van annual license is not included in the cost of new wan. Thus, it is not consider in the computation part.
Hence, Schrock record the $65,920 as the cost of the new van
Answer:
More likely
Explanation:
If the current market price of a stock is higher than the intrinsic value of that stock, it is less likely to receive a hostile takeover bid. On the other hand, if the current market price of a stock is lower than the intrinsic value of that stock, it is more likely to receive a hostile takeover bid. The reason is that the intrinsic value is the decision-making tool for the investors, which helps the investors to invest in that company.
Full question attached:
Answer attached
Answer and Explanation:
ES= earliest start time
LS=latest start time
EF= earliest finish time
LF= latest finish time
in calculating earliest start time, we look at predecessor to the task, for example c has a predecessor of A and so ES would be after A=3.in calculating our earliest start time and latest finish time we have used the forward pass and backward pass method respectively. The forward pass method uses the latest of the predecessors earliest finish in calculating ES while the backward pass method uses the earliest of the successors latest start(LS)in calculating latest finish(LF)
EF=ES+time
LS=LF-time
slack=LF-EF
The Critical path is ADEG identified by zero slacks
project duration is equal to duration of critical path equal to 15