Answer:
Variable overhead efficiency variance= $3,000 favorable
Explanation:
<u>To calculate the variable overhead efficiency variance, we need to use the following formula:</u>
Variable overhead efficiency variance= (Standard Quantity - Actual Quantity)*Standard rate
Standard quantity= 3*15,000= 45,000 hours
Actual quantity= 44,000 hours
Standard rate= $3 per hour
Variable overhead efficiency variance= (45,000 - 44,000)*3
Variable overhead efficiency variance= $3,000 favorable
Answer:
Retained earnings-Closing = $19,900
Explanation:
Given that,
Revenues = $22,400
Operating Expenses = $15,000
Dividends = $4,500
Retained Earnings(opening) = $17,000
Net Income = Revenues - Operating expenses
= $ 22,400 - $15,000
= $7,400
Statement of Retained Earnings:
Retained earnings-Closing:
= Retained earnings -opening + Net Income - Dividends
= $17,000 + $7,400 - $4,500
= $19,900
Answer:
4.51
Explanation:
We have to calculate fva. The future value of annuity
Here is the formula
Fva = A [( + I)^n-1/I]
Where a = annuity
I = interest rate
N = number of years
Inserting into formula
1[(1+0.08)^4 - 1/0.08]
= 1[(1.36049 - 1)/0.08]
= 4.51
Therefore the future investment is $4.51
I believe the answer should be C. autonomy.