Answer:
1245?
Step-by-step explanation:
30% of $4,150
Answer:
a) See attachment 1.
b) t² and D
c) See attachment 2.
d) g = 9.8 m/s² (1 d.p.)
Step-by-step explanation:
<h3><u>Part (a)</u></h3>
See attachment 1. The line of best fit is shown in red.
<h3><u>Part (b)</u></h3>
The quantities the student should graph in order to produce a <u>linear relationship</u> between the two quantities are t² and D.
<h3><u>Part (c)</u></h3>
Make a table of values of t² and D:

<u>Plot</u> a graph of D against t² and draw a line of best fit (see attachment 2).
<h3><u>Part (d)</u></h3>
From inspection of the graph, the line of best fit passes through the origin (0, 0) and (0.1024, 5.0). Therefore, use these two points to find the slope of the line:

Therefore:



Look at the tenths place when rounding to the nearest whole number. It is larger than 5 so round up. It will be 57.
Answer:
of which class is it ?
Step-by-step explanation:
???????.................
Answer:
10 days to complete
Step-by-step explanation:
for mixed rate problems, the sum of each individual reciprocal rates equals the sum of the combined rate
i.e

we are given,
A's rate = 15 days to complete
Combined rate = 6 days to complete
B's rate = need to find
substituting' the given info into the equation above,
1/15 + 1/ (B's Rate) = 1/6
1 / (B's Rate) = 1/6 - 1/15 (convert right side to same denominator)
1 / (B's Rate) = 5/30 - 2/30
1 / (B's Rate) = 3/30
1 / (B's Rate) = 1/10 (taking reciprocal of both sides)
B's rate = 10 days to complete