Answer:
Step-by-step explanation:
3b⁵ + 15b⁴ - 18b⁷ = 3b⁵ + [3*5*b⁴] - [6*3*b⁷]
=3b⁴*( b + 5 - 6b³)
I guess this is what you mean 3√a^10 and 3√b^7
Answer:
2
Step-by-step explanation:
(4)(−2)+10
=−8+10
=2
First, you need to get rid of the fraction by multiplying both sides by 20 and you would get:
4(x + 2) = 5(x + 6)
Now, you need to get rid of the parenthesis by distributing:
4x + 8 = 5x + 30
Subtract both sides by 5x:
-x + 8 = 30
Subtract both sides by 8:
-x = 22
Now, divide both sides by -1:
x = -22
P.S.: You don't really need a calculator to solve.
9514 1404 393
Answer:
9 weeks
Step-by-step explanation:
In problems of this nature, the usual assumption is that the time required is proportional to the work product and inversely proportional to the number of people doing the job. Here, there is no change in the amount of work, but the number of people is reduced by a factor of 12/18 = 2/3.
So, the amount of time required is expected to increase by a factor of 1/(2/3) = 3/2.
(6 weeks)×(3/2) = 9 weeks
It would have taken 9 weeks to sew the 540 dresses.