The solution to the growing amount of data in software applications to have fully sustainable usage for customers is;
- Development of a sustainable model for the future now requires data storage that is engineered to be lower power requirements, lower cooling requirements, and lower waste production.
<h3>Sustainable data storage and usage</h3>
The objective of Sustainable Data Storage Initiative is to spread awareness of the solutions that can reduce the environmental impact of high waste producing data centers.
The environmental impact of data infrastructure is growing as data workloads increase. Hence, building a sustainable model for the future now requires data storage that is engineered to be lower power requirements, lower cooling requirements, and lower waste production.
Read more on Sustainable data storage and usage;
brainly.com/question/24882256
If a terminal emulation program is used and the devices should be reotely managed, then you should use the Telnet protocol. <span>Telnet is a simple, text-based network protocol that is used for accessing remote computers over TCP/IP networks like the Internet. </span>It allows the user access<span> to a text terminal and all its </span>applications<span> such as command-line for example. </span>
La unidad de medida de energía oficial es el Joule (J). El kilovatio / hora (kWh), utilizado especialmente para la energía eléctrica, debe figurar entre las unidades más comunes de medición de energía (de hecho, se utiliza para calcular las facturas de electricidad). Entonces es B.
Answer:
See explanation below
Explanation:
Previos concepts
First Come First Serve (FCFS) "is an operating system scheduling algorithm that automatically executes queued requests and processes in order of their arrival".
Shortest job next (SJN), or the shortest job first (SJF) or shortest "is a scheduling policy that selects for execution the waiting process with the smallest execution time".
Shortest remaining time (SRF) "is a scheduling method that is a preemptive version of shortest job next scheduling'".
Round robin (RR) is an algorithm where the time parts "are assigned to each process in equal portions and in circular order, handling all processes without priority"
Solution for the problem
Assuming the dataset given on the plot attached.
Part a
For this algorithm the result would be:
Job A 0-6
Job B 6-(6+3) = 6-9
Job C 9-(9+1) = 9-10
Job D 10-(10+4) = 10-14
Part b
For this algorithm the result would be:
Job A 0-6
Job C 6-(6+1) = 6-7
Job B 7-(7+3) = 7-10
Job D 10-(10+4) = 10-14
Part c
For this algorithm the result would be:
Job A 0-1 until 14
Job B 2-(2+3) = 2-5
Job C 3-(3+2) = 3-5
Job D 9-(9+5) = 9-14
Part d
For this algorithm the result would be:
Job A 0-2 , 7-9, 12-14
Job B 2-4, 9-10
Job C 4-(4+1) = 4-5
Job D 5-7, 10-12
Answer:
Please see the attached file for the complete answer.
Explanation: