Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
It would be 60 because all you do is double the radius because it is only half of the circle
Answer:
A
Step-by-step explanation:
AB ll CD
what grade r u in btw ?
Step-by-step explanation:
Volume= [(20+20) x (20+20) x 100] - (20 x 20 x 100)
=120000cm^3
surface area= 2 x 40 x 100 + 2 x (40 x 40 - 20 x 20) + 4 x 20 x 100
=18400cm^2
Answer:
so u wanna date ;)
Step-by-step explanation: