The term NComputing is known to be a form of desktop virtualization company that is said to creates hardware and software to form virtual desktops.
The term Thin clients is known to be virtual desktops. They help a lot of users at the same time to share a single operating system instance.
<h3>What is the aim of a thin client?</h3>
In Ncomputer networking, a thin client is known to be a kind of low-performance computer that is known to be optimized and used for setting up a remote connection.
It is often used with a server-based computing system. The server here is one that often does most of the work, such as launching software programs, etc.
Learn more about Ncomputing from
brainly.com/question/12629145
Members of an Agile development team often agrees on what tasks to work on and they do it together. The one possible solution to this challenge is to Have the database developer train the rest of the team so there are fewer handoffs.
Agile development team often works together as a team. They as team discuss the task yo take, when it will take place etc.
This team is all about communication, teamwork, problem-solving etc.
Conclusively, A task should be completed by one member on the team, but the team may choose to pair up when doing the work.
Learn more from
brainly.com/question/24383225
See full question below:
Your agile team only has one person who knows how to develop database software. So the other developers finish their tasks and then wait for their work to be Integrated into the database. This creates a pile of backed up work for the database developer. But it also means that the other developers must either wait or add to the growing pile of database work. What's one possible solution to this challenge?
Select an answer:
Have the database developer train the rest of the team so there are fewer handoffs.
Have the software developers split their time between other teams so they're not as productive
Encourage the database developer to work overtime to catch up with their work.
Create a large batch of work so the database developer can focus on finishing
Answer:
The correct answer is C) With respect to PERT and CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.
Explanation:
The CPM (Critical Path Method) method is frequently used in the development and control of projects whose tasks have a fixed duration while the PERT (Program Evaluation and Review Techniques) method is a set of techniques with the same purpose but that allows to work with tasks with estimated probability duration but not deterministic.
Both methods are based on developing a complete scheme that includes all the tasks of a project linked to each other according to their sequence, determining the duration and analyzing different ways of reconfiguring the task planning to optimize the use of the resources of according to the general objectives of the project.
There are tasks that to start performing them must have been completed one or more previous tasks. The overall duration of the project is determined by the Critical Path, which is the sequence of tasks of greater duration. The tasks belonging to the critical path have to be carried out with special care because delays in them would cause delays in the total achievement of the project. That is why these tasks have no slack.
The rest of the tasks have some slack, which is determined by the time that a previous task can be delayed without delaying the total time of completion of the project, that is, not exceeding the duration determined by the critical path.
That is that why we say that the <em>slack</em><em> is the amount of time a task may be delayed without changing the overall project completion time</em>.
My guess would be B and D.
Answer:
1) Avoid the perfectionist of trap
2)Banish the negative thoughts
3) Get enough sleep
4) Make sure you are prepared
5) take deep breaths
Explanation:
In my thought it's the answer of this question.