Answer:
5,874,589,152,000 mi.
Step-by-step explanation:
The diameter is 80 or the first answer
Total cost of job=$231.08
Labor time= 6 1/2 = 6.5 hours
Overhead=55%
Retail price of parts=$114.70
Find the total cost of labor.
Total cost of labor= 231.08 - 114.70=$116.38
Now labor rate per hour ( with overhead)= 116.38 /6.5 =$17.90 per hour.
Now labor rate (without overhead) = 17.90/(1+55%) = 17.90/1.55 =$11.55
Answer: $11.55