Answer:
The actual price = $1.08
Explanation:
The standard material price can be worked out as follows:
<em>Step 1: Work out the standard price of material using the material usage variance</em>
Standard price = Material usage variance/(standard quantity of material - actual quantity)
Standard quantity of material = standard qty per unit × actual production
= 4 × 17,000 =68,000
Standard price = 2,800/(68,000-64,000)= $0.7
<em>Step 2 : Work out the Actual material price using the material price variance</em>
Material price variance = (Standard price - Actual price )× Actual quantity of material
6,400 = (y - 0.7) × 17,000
6400 = 17,000y - 11,900
17,000 y = 6,400 + 11,900
y = 18,300/17,000= 1.08
The actual price = $1.08
Answer:
...when that project will have the same level of risk as the firm's current operations
Explanation:
Weighted average cost of capital (WACC) is the company's cost of capital based on its proportion of equity and debt used in its capital structure. It can be used as the discount rate for calculating the present value of future expected cashflows of a project if the project is determined to be of similar risk to the company's operations; meaning that the estimated beta of the project is the same as the beta of the firm.
Answer:
$30,000
Explanation:
The computation is shown below:
As we know that
Current ratio = Current assets ÷ Current liabilities
Current assets = 3.4 × Current liabilities
Now the
Acid-test ratio = Quick assets ÷ Current liabilities
2.8 = Currents assets - inventory ÷ Current liabilities
2.8 = 3.4 × Current liabilities - $18,000 ÷ Current liabilities
2.8 × Current liabilities = 3.4 × Current liabilities - $18,000
After solving this, the current liabilities is $30,000