Answer:
0.726 is the probability that the project will be completed in 33 days or less.
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 30 days
Variance = 25 days
Standard Deviation,

We assume that the distribution of path length is a bell shaped distribution that is a normal distribution.
Formula:

P(completed in 33 days or less)
Calculation the value from standard normal z table, we have,

0.726 is the probability that the project will be completed in 33 days or less.
because in each case, the selected column composes one<span>-tenth of the grid in total. The number of blocks is different, but the proportion of space filled is the same.</span>
I’m pretty sure your answer will be -7 because if you add the negatives together it will get more negative and -3 and -4 combined is -7
Answer:
wait, it only 25 points...
Step-by-step explanation:
Take 2 points: (0, 70) (30, 80)
SLOPE FORMULA: y2 -y1 / x2 - x1
y2 - y1: 80 - 70 = 10
x2 - x1: 30-0 = 30
10 / 30
simplify: 1/3
This is a PROPER FRACTION