A 3 I guess or a B. idk....
Answer:
So to maximize profit 24 downhill and 20 cross country shouldbe produced
Step-by-step explanation:
Let X be the number of downhill skis and Y the number of cross country skis.
Time required for manufacturing and finishing each ski are: manufacturing time per ski, downhill 2.5 hours, cross country 1.5 hours
Finishing time per ski: downhill 0.5 hours, cross country 1.5 hours.
Total manufacturing time taken = (2.5) x+ (1.5+) y = 2.5x+1.5y≤90
total finishing time taken = 0.5x+1.5 y≤42
Profit function
Z = 50x+50y
Objective is to maximize Z
Solving the two equations we get intersecting point is
(x,y) = (24,20)
In the feasible region corner points are (0.28) (36,0)
Profit for these points are
i) 2200 for (24,20)
ii) 1400 for (0,28)
iii) 1800 for (36,0)
So to maximize profit 24 downhill and 20 cross country shouldbe produced.
Answer:

Step-by-step explanation:
The equation of a circle is given by:

Where (h, k) is the center and r is the radius.
The center of the circle is (1, -4).
And the radius is 3.
Substitute:

Simplify. Thus, our equation is:

Answer:
y > -x + 3
Step-by-step explanation:
find the slope and y-intercept so you can create a linear equation:
y = mx + b ; m = slope and b = y-intercept
slope (m) = (3-0) / (0-3)
m = 3/-3 or -1
we can see the y-intercept by looking at the graph, it is 3
y > -x + 3