I believe you meant "why is the number of shifts multiplied by approximately 4.5 to obtain the total number of operators required to run the plant"
Answer and Explanation:
There are 3 shifts per day, 49 weeks per year and 5 shifts per operator per week
To get total number of operators required to run the plant, we multiply number of shifts in a year by number if operators per shift.
49 weeks×5 shifts= 245 shifts per operator per year
365×3 shifts= 1095 shifts per year
1095/245=4.5 operators per shift
total number of operators required to run the plant(per day) = 4.5×3= 13.5 approximately 14
total number of operators required to run the plant(per year) =4.5×1095=4927.5 approximately 4928
Type o ( ii) = 6 . 25
Type A ( l^A l ^A or l ^A i ) = 18 . 75
Type B ( l ^b l^b or l ^ bi ) = 18.75
Type AB ( l ^ A l^ B) = 56.25
Answer:
4. 18-(-12)
Step-by-step explanation:
so i basically took 12 and added that to 18 [and got 30] to find out how many degrees it went up and then i solved each equation till i got 30. I hope this helped and that you could understand the way i did it.
Answer:
y=5
m<A= 25
m<E= 35
Step-by-step explanation:
since <E equals <B due to CPCTC the equation:
3y+20=10+5y
is the equation
I believe the answer is D
Because 24x4 is 96