<span>The organization that requires a 90-day supply of oil is the International Energy Agency (IEA). Each country in the organization must stock an amount of petroleum equivalent to this amount because of the organization's obligations.</span>
Answer:
1. $6,000
2. $60
3. $8,180
Explanation:
With the down payment equal to $2,000, amount Lindsay need finance to purchase car would be: $8,000 - $2,000 = $6,000
As Lindsay would pay for a term of 3 years
=> In each year, the amount finance is: $2,000
In one year, with APR = 3%, interest Lindsay has to pay on the loan of $2,000 is: $2,000 x 3% = $60
=> In three years, amount Lindsay pay for interest for the total finance is: $60 x 3 = $180
The actual cost of the car for Lindsay to own:
Actual cost = down payment + finance + interest = $2,000 + $6,000 + $180
= $8,180
Answer:
The interest rate is 11%
Explanation:
The loan amount = $50000
Interest amount = $5500
Since the annual interest amount and the principal amount is given so we have to find the interest rate by using the given information. Below is the formula to find the interest rate.
Let the interest rate = x
Principal × interest rate = Interest amount
$50000 × r = $5500
r = $5500 / $50000
r = 0.11 or 11%
The interest rate is 11%
Answer:
a prior period adjustment
Explanation:
A prior period adjustment -
It is the correction of the accounting error which took place in the past and was written in the prior year of financial statement , net of the income taxes , is known as a prior period adjustment .
It is the method to fix the previous problem of past during the reporting .
hence , the correct term fro the given statement is a prior period adjustment .
The correct answer is D) maintain a uniform level of required resources.
The start of noncritical activities is delayed beyond their earliest start times (but not beyond their latest start times) in order to maintain a uniform level of required resources.
That is why companies have to establish their priorities and identify the main activities that must be accomplished on time, the people responsible to accomplish the activity, and the resources needed to successfully do so. Noncritical activities can be delayed up to a point, but the critical activities have to be followed according to the schedule.