Answer:
It takes 5 days to process an application.
Step-by-step explanation:
We have that number of requests per month would be equal 1600
Now, the applications in hand would be:
160 + 240 = 400
They tell us that everything must be in a number of 20 business days, therefore, the number of applications in one day would be:
1600/20 = 80
Which means that the time needed to finish an application is:
400/80 = 5 days
It takes 5 days to process an application.