Bar chart.
Pie chart.
Line chart.
Answer:
automated
Explanation:
Basically a Business Impact Analysis (BIA) estimates and determines the effects of a business activity and process disturbances. These disruptions can be natural or electronic disasters. It also collects information which is used to establish recovery plan. It identifies the business vulnerabilities and works on the strategies in order to reduce such potential hazards. The BIA involves both manual and automated processes. BIA involves automated processes which include the automated software tools that enables the protection of the confidential information of the users and also generates automated reports about the critical business processes.
(Disclaimer: I am not a professional, so it might not be the most concise answer possible, but I did run the Python script and it works)
Answer:
user_input = input("What food do you have in your refrigerator? ").lower()
count = 0
while True:
if user_input != 'apples':
count += 1
print(f'You have a {user_input} with a total of {count} food(s)\n')
user_input = input("What food do you have in your refrigerator? ")
else:
break
Answer:
The correct option is A
Explanation:
In project management, earliest finish time for activity A refers to the earliest start time for succeeding activities such as B and C to start.
Assume that activities A and B comes before C, the earliest finish time for C can be arrived at by computing the earliest start-finish (critical path) of the activity with the largest EF.
That is, if two activities (A and B) come before activity C, one can estimate how long it's going to take to complete activity C if ones knows how long activity B will take (being the activity with the largest earliest finish time).
Cheers!