Answer:
0.61
Step-by-step explanation:
The computation of the probability of the working of the system is shown below:
But before that first we have to find out the total probability of sub-system i.e 2,3 and 4 i.e

= 0.48
Now the working of the system probability is
= 1 - [(1 - probability of component 1) × (1 - sub system probability)]
= 1 - [(1 - 0.75) × (1 - 0.48)]
= 1 - 0.39
= 0.61
Please find the attachment for better understanding.
Answer:
the slope is 3
Step-by-step explanation:
Answer:
$5809.17
$6149.01
$2211.72
Step-by-step explanation:
Continous interest formula:
(pv)e^(rt)
we have
5000e^(5*.03)= 5809.17
Same equation from before
2500e^(.09*10)= 6149.01
2000e^(.0575*(21/12))
(we write 21/12 because that's how many years has passed)
= 2211.72
Answer:
148^2
Step-by-step explanation:
2(lb+bh+lh) = 2(4*5+5*6+4*6)=148 in^2