Answer:
a.9.313hr
b.116.4%
c.104.0%
Explanation:
(a) Hstd= 75(7.45)/60 = 558.75/60 = 9.313 hr
(b) Ew= 9.313/8.0 = 1.164 = 116.4%
(c) Time worked = 480 – 13 = 467 min
Tc= (467 min)/(75 pc) = 6.227 min/pc
Tn= 7.45/(1 + 0.15) = 6.478 min/pc
Pw= 6.478/6.227 = 1.040 = 104.0%
Using a credit card is like borrowing money, while debit cards let you draw directly from your bank account
Answer:
A. $125
(Supplies + Electricity)
B. $10,300
(Salary lost + Rent amount lost)
C. $10,425
(Add them together)
Answer:
Overhead costs are often affected by many issues and are frequently too complex to be explained by any one factor.
Explanation:
An overhead cost is not directly defined, to be that of material, or labor, or any other unit, overhead include, many factors, electricity usage, machine hours usage, water usage, or the capacity utilization of machinery, and various other factors. Since its computation and allocation is not clear many a times, a single overhead like that of electricity, has many factors, ideal usage of electricity, or machine hours used in production or simply the total cost of overheads for that month or building or etc: and its utilization. In short, to conclude we can state that overhead costs are complex in nature.
All other options are false.
Final Answer
Overhead costs are often affected by many issues and are frequently too complex to be explained by any one factor.
Answer:
"$ 15,000" is the correct solution.
Explanation:
The given values are:
Agreed fixed rate,
= 0.04
LIBOR rate,
= 0.01
No. of borrowing months,
= 6
National amount,
= 1000000
Now,
The net payment will be:
= 
On substituting the above values, we get
= 
= 
=
($)