Answer:
<u>A and B are correct</u>
Explanation :
- The TVM concept is based on the value of money which is today may change with time as a rise or fall in prices thus this explains why the interest rates are paid and calculated on the basis of the present values that may change such as future sum of money of cash flows, can get discontinued at the discounted rates.
- Future values can be ascertained based on the present value of the product/assert. Thus the interest rates and inflation rates change as the risks and the consumer's needs will always be present and have existed earlier.
- It's calculated by the present value and future value of money multiplied by the interest rate and the total number of years. I.e
- FV = PV x [ 1 + (i / n) ] (n x t)
Answer:
C.105,500 units
Explanation:
Equivalent unit of production is the quantity of work done in the manufacturing / production department. It also includes the completed percentage portion of the units in work in process.
Units complete and transferred = Beginning units + Additions - uncompleted units = 10,000 units + 100,0000 units - 15,000 units = 95,000 units
Equivalent Units = Units complete and transferred + ( Closing units x percentage completion )
Equivalent Units = 95,000 + ( 15,000 x 70% )
Equivalent Units = 95,000 + 10,500
Equivalent Units = 105,500
Answer:
$6.40
Explanation:
In this case, the predetermined overhead rate is calculated by dividing total manufacturing overhead expense by the total number of direct labor hours. The overhead expense is divided in two: fixed and variable. Predetermined variable overhead expense is $2.80 and predetermined fixed overhead expense = $36,000 / 10,000 direct labor hours = $3.60.
So the total predetermined overhead rate = $2.80 + $3.60 = $6.40