Answer:
the required probability is 0.09
Option a) 0.09 is the correct Answer.
Step-by-step explanation:
Given that;
mean μ = 7
x = 4
the probability of exactly 4 bridge construction projects taking place at one time in this state = ?
Using the Poisson probability formula;
P( X=x ) = ( e^-μ × u^x) / x!
we substitute
P(X = 4) = (e⁻⁷ × 7⁴) / 4!
= 2.1894 / 24
= 0.0875 ≈ 0.09
Therefore the required probability is 0.09
Option a) 0.09 is the correct Answer.
Answer:
Step-by-step explanation:
y = -2x+5
slope of line is -2.
slope of parallel to line is also -2
point-slope equation for line of slope -2 that passes through (-5,3):
y-3 = -2(x+5)
Answer:
The weight of box and pocking material pound
Step-by-step explanation:
Let the weight of box and packing material
weight of package pounds
total weight pound
Subtract both side by
Hence weight of box and packing material pound
I think this might work 440=55x-275 then solve