Answer:
$76,260
Explanation:
Calculation to determine the total period cost for the month under variable costing
Using this formula
Total Period cost = Variable selling and administrative cost + Fixed manufacturing overhead + Fixed selling and administrative cost
Let plug in the formula
Total Period cost = ($14 × 1,760) + $18,180 + $33,440
Total Period cost =$24,640+$18,180 + $33,440
Total Period cost =$76,260
Therefore the total period cost for the month under variable costing is $76,260
Answer:
An associate's or bachelor's degree in early childhood education is needed to work as a child care director.
Explanation:
Answer: Option B
Explanation: Competitive intelligence refers to the study of different factors of the business environment by the organisation for helping the senior management to make strategic decision making.
This study analyzes the factors that directly affects the organisation. The channel of distribution of the competitor can be used to understand their strategy for making their market. An organisation could use this information by improving their channel and gaining a competitive advantage.
Hence from the above we can conclude that the correct option is B
Answer:
The NPV from opening the branch office is negative ( -$106668.08). Thus the branch office should not be opened.
Explanation:
The decision to open the branch office will be taken based on the NPV provided by opening of the branch office. If the NPV of a project is positive based on the required rate of return used as a discount rate fro cash flows, the investment is worth undertaking.
The net present value (NPV) for a project can be calculated as,
NPV = CF1 / (1+r) + CF2 / (1+r)² + ... + CFn / (1+r)^n - Initial Outlay
Where,
- r is the appropriate discount rate
- Initial Outlay is the Initial cost of the project
- CF represents cash flows from the project
As the required return is 16%, we will take this as the appropriate discount rate.
NPV = 45000 / (1+0.16) + 120000 / (1+0.16)² + 150000 / (1+0.16)³ +
150000 / (1+0.16)^4 + 150000 / (1+0.16)^5 - 485000
NPV = - $106668.08
As the NPV from project is negative at a required return of 16%, the project should not be under taken and the branch office should not be open.