Answer:
Average time per unit is 59.6 hours
Explanation:
As we know as the work is done the learning of the labor force increases and they require less time to produce the next unit. An average time required to produce specific numbers of unit including cumulative effect of the learning curve.
As per given data
Number of units = 30 unit
Ratio of Time to produce second unit = 90 / 100 = 0.9
Accumulated Average time per unit Formula is
y = aX^b
Where
y = Average time per unit = ?
X = Cumulative Numbers of unit = 30
a = Time required to produce first unit = 100 hours
b = factor used to calculate cumulative average time = log (Learning Curve %/ log2) = Log (90/100) / Log2 = -0.152
Place value value in the formula
y = 100 x 30^ -0.152 = 59.6 hours
Answer:
a) Is Santhosh required to increase his withholding or make estimated tax payments this year to avoid the underpayment penalty?
- No he is not required to make any payments or increase his withholdings because this year's withholdings already represent a 133% increase with respect to last year's tax liability. If the withholdings for the current are over 100% last year's tax liability, then the taxpayer doesn't need to make any further adjustments in order to avoid underpayment penalties.
b) By how much, if any, must Santhosh increase his withholding and/or estimated tax payments for the year to avoid underpayment penalties?
Answer:
The American Recovery and Reinvestment Act of 2009 (Recovery Act) - which President Obama signed into law on February 17th, 2009 - was an unprecedented action to stimulate the economy. It included measures to modernize our nation's energy and communication infrastructure and enhance energy independence.
Explanation:
Answer:
$12,000 plus tax money
Explanation:
I don't know this but I am always trying to help. she will get $12,000 combined and also more money because of plus the money she will get with taxes.