Answer:
$455,000
Explanation:
Given that,
high speed industrial centrifuge at a cost = $420,000
Shipping costs = $15,000
Foundation work = $8,000
additional water line = $3,000
Labor and testing costs = $6,000
Materials used up in testing = $3,000
Total Costs to be capitalized:
= High-speed industrial centrifuge + Shipping costs + Foundation Work + Additional Water Line + Labor and testing costs + Materials used in testing
= $420,000 + $15,000 + $8,000 + $3,000 + $6,000 + $3,000
= $455,000
Answer:C) $2,125.
Explanation:
Interest = Principal x rate x time (period)
using days in a year = 360 days
Interest = $85,000 X 10% x 90/360
=$2,125
Therefore, Alabaster Inc, must repay the $85,000 principle and $2,125 in interest
The last step in making a personal budget is to reduce expenses in flexible categories. The correct option among all the options given in the question is option "B". Under normal circumstances, a person cannot make the adding up all sources of income as the last step. Then the expenses will not get added. The flexible expenses are expenses that can always be reduce or are not important expenses. The basis of making the budget is to reduce those unnecessary expenses. So the last step should always be to find ways to reduce the flexible or unwanted expenses.
Answer:
Year Cash Flow (A) Cash Flow (B)
0 -37,500 -37,500
1 17,300 5,700
2 16,200 12,900
3 13,800 16,300
4 7,600 27,500
1) Using an excel spreadsheet and the IRR function:
IRR project A = 20%
IRR project B = 19%
2) Using the IRR decision rule, Bruin should choose project A.
3) In this case, since the length of the projects is only 4 years, then there should be no problem with the IRR decision rule, but for projects with longer time lengths, the discounts rates might vary and the best option is to use the modified internal rate of return (MIRR). But in this case the NPV of project B is higher, then Bruin should probably project B because it has a higher NPV. The NPV is always more important then the IRR.
4) Again using an excel spreadsheet and the NPV function:
NPV project A = $6,331
NPV project B = $8,139
5) first we must subtract cash flows from A by the cash flows from B:
1 $11,600
2 $3,300
3 -$2,500
4 -$19,900
then we calculate the IRR = 16%
Bruin should be indifferent between the two projects at a 16% discount rate. That means that at discount rates above 16%, you should choose project A, but at discount rates below 16%, you should choose project B
Answer:
1,065 U
Explanation:
Materials Price Variance = Actual Quantity Purchased * (Standard Price – Actual Price)Actual Price= Total Cost / Quantity Purchased
= ($27,690 /21,300 )=$ 1.3
=21,300* [$1.25 – $1.3]
=21,300*0.05
=1,065 U
During May, the materials price variance for part XBEZ52 was 1,065 which is Unfavourable because the actual
purchase price is higher than standard.