I WILL MARK BRAINLEST!! ONLY 5 MINS!!

Mathematics
1 answer:
ad-work [718]3 years ago
6 0

Answer: The last answer choice maybe

Step-by-step explanation:

Mean  9

Median  10

Mode 10

You might be interested in
Which of the following are polynomial functions? Check all that apply.
arsen [322]

Answer: B, C, E

Step-by-step explanation:

8 0
4 years ago
1/4 x 2/5=
Zanzabum

Answer:

1/10

Step-by-step explanation:

The answer is 1/10 because multiply the numerator and got 2 and then the denomi actors and got 20.

So it would be 2/20.

Then you simplify 2/20 to 1/10

2÷2=1

20÷2÷10

Then you get 1/10.

Hope i helped

8 0
3 years ago
Can anyone help me with my Geometry question?
WITCHER [35]

Answer:

5.37ft^2

Step-by-step explanation:

Area of the square minus area of the circle, so...

Area of the square is 5x5=25

Area of the circle is pi*2.5^2=19.63

25-19.63=5.37ft^2

7 0
3 years ago
Read 2 more answers
The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. Th
matrenka [14]

Answer: the due date would be 92 weeks

Step-by-step explanation:

Since the time required to complete a project is normally distributed, we would apply the formula for normal distribution which is expressed as

z = (x - µ)/σ

Where

x = number of weeks.

µ = mean

σ = standard deviation

From the information given,

µ = 80 weeks

σ = 10 weeks

If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, the z score corresponding to 90%(90/100 = 0.9) is 1.29

Therefore,

1.29 = (x - 80)/10

x - 80 = 1.2 × 10

x - 80 = 12

x = 80 + 12 = 92

5 0
3 years ago
At the beginning of the month, Kimberly had $65.78. Since then,she has received three payments of $32.50 from her babysitting jo
lys-0071 [83]

Answers:

she has $80.78.

Step-by-step explanation:

5 0
3 years ago
Other questions:
  • (20 points)
    8·2 answers
  • Elle and heather drew floor models of there living rooms.Elles model respresented 20 feet by 15 feet.Heathers model respresented
    9·1 answer
  • In how many minutes will a heart beat in 140 times?
    7·2 answers
  • Let's say we have two similar shapes. We'll call them Shape 1 and Shape 2. Shape 1 have the following characteristics: P1 = 22 m
    9·1 answer
  • Which expression is equivalent to the number 360?
    5·1 answer
  • With the process<br>opt maths​
    9·1 answer
  • Thianamccornell1 no one else
    15·1 answer
  • Find a polynomial f(x) of degree 4 that has the following zeros. 7, −3, 0, −2
    10·1 answer
  • Can someone please tell me the answer <br> (-42)-(+16)=
    12·2 answers
  • Find the measure of angle x in the figure below:<br><br> A) 35<br> B) 47<br> C) 51<br> D) 62
    14·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!