Answer:
the first one
Step-by-step explanation:
A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.
The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.
The second graph does not appropriately account for duration of predecessor tasks.
The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).
Answer:
According to the passage, we have the next equation:

where "K" is a proportional constant
Leaving at the end with the next equation:

Integrating the equation, we have:

where "C" is a constant
Then, we have the 2 conditions for the problem:
1) t=0 → r=10
Replacing in the equation, we have C = 10
2) t=5 → r=8
Replacing in the equation, we have K = -0.4
Finally, the time which the snowball will be completely melted will be when r = 0. So replacing in the equation

t = 25 minutes
Answer:
−4
Step-by-step explanation:
Answer:
D ($46.19)
Step-by-step explanation:
$124.85 * (100% - 63%)
= $124.85 * 37 %
= $124.85 * 0.37
= 46.1945
= $46.19 (to the nearest cent)
Hope this helped!
The first one as the first number must be >= 1 Here it is 0.2.