Answer:
For A. and B see attached files
Explanation:
Answer:
Correct option is (B)
Explanation:
Given:
Beginning capital = $80,000
Net income = $35,000
Drawings = $18,000
Net income is added to opening capital and deduct drawings to arrive at capital balance at the end.
Capital at the end of the year = opening capital + net income - drawings
= 80,000 + 35,000 - 18,000
= $97,000
The capital projects fund account for the 10 percent retainage as (B) II only.
<h3>
What is retainage?</h3>
- Retainage is a percentage of the agreed-upon contract price withheld until the work is substantially completed to ensure that the contractor or subcontractor will fulfill its responsibilities and complete a construction project.
- Retention is money kept back by one party in a contract as security for unfinished or defective work.
- Assume the contract is worth $20,000 and you're submitting a paid app after finishing 25% of the work.
- So you earned $5,000 during the pay period, but retainage is 5%. The current progress payment has been reduced by $250.
- As a result, the "Amount Due for this Request" will be $4,750.
So, in the given situation the capital projects fund account for the 10 percent retainage as (II) the credit for $400,000 to Contracts Payable-Retained Percentage, that is (B) II only.
Therefore, the capital projects fund account for the 10 percent retainage as (B) II only.
Know more about retainage here:
brainly.com/question/24101126
#SPJ4
The correct question is given below:
The capital projects fund of Hood River completed the construction of an addition to its city hall at a cost of $4,000,000. The city council approved payment of the amount due to the general contractor, less a 10 percent retainage. How should the capital projects fund account for the 10 percent retainage?
I. As a credit of $400,000 to Deferred Revenue-Retained Percentage
II. As the credit for $400,000 to Contracts Payable-Retained Percentage.
A. I only
B. II only
C. Either I or II
D. Neither I nor II
Answer:
A. the change in the value of the optimal solution.
Explanation:
- A shadow pricing is associated with each constraint of the model and is the instantaneous changes that occur in the objective model of the optimal solution that is obtained by changing the right-hand side constrained by one unit and a reduced cost is associated with each variable of the model. Also referred to as a monetary values that is assigned to the current unknowable or difficult to calculate costs.