Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
If they must pay for property's real estate taxes and premiums for insuring the building. The type of lease xyz company sign is:<u> Double net lease.</u>
<h3>What is Double net lease?</h3>
Double net lease can be defined as form of agreement that occur between a tenant and a landlord were the tenant agrees to pay for the cost of rent while the landlord on the other hand agrees to pay for operating expenses incurred by the tenant.
Based on the given scenario the type of the lease xyz company sign is called double net lease as they have to pay for property's real estate taxes as well premiums for insuring the building.
Therefore the type of lease xyz company sign is:<u> Double net lease.</u>
Learn more about double net lease here:brainly.com/question/14244511
#SPJ1
Answer:
(C) target market
Explanation:
The group of people for which a product is designed and aimed to is the product's target market. In this case, Topik is a product that aims to sell to blue-collar workers who earn less than $30,000 per year, are divorced, and who like to think of themselves as weekend athletes, which is the product's target market.
The answer is (C).