Answer:
Land = $295,000
Building = $1,375,000
Explanation:
The computation of cost of the land and new building is shown below:-
Land = Parcel of land + Demolition of old building + Legal fees for title investigation and purchase contract - Salvaged materials resulting from demolition were sold
= $280,000 + $20,000 + $5,000 - $10,000
= $305,000 - $10,000
= $295,000
Building = Architect's fees + Construction costs
= $35,000 + $1,340,000
= $1,375,000
We simply applied the above formulas
Answer:
invoice price (dirty price) = $1,004.13
Explanation:
semi-annual coupon = $1,000 x 7% x 1/2 = $35
clean price = $1,001.25
accrued interest = (Jan. 30 - Jan. 15) x $35 x 1/182 = $2.88
invoice price (dirty price) = clean price + accrued interest = $1,001.25 + $2.88 = $1,004.13
the dirty price or invoice price of a bond includes any accrued interest that the bond may have earned in the period between the last coupon payment and the transaction date.
Answer:
There are two types of profit and costs in nay business, which are accounting costs/profit and the economic costs/profits.
Accounting costs include everything that is tangible or the monetary costs a firm pays, while the economic costs include the cost which is intangible(Opportunity costs) as well as tangible.
Here in this question, the profit of the firm therefore is,
a. From an accountant;s definition = 130000-(6000+42000+7000) = 75000.
b. From an economist's definition = 130000-(6000+42000+7000+65000+6000) = 4000.
Hope this helps you. Thankyou.
Answer:
$120 per unit
Explanation:
The computation of minimum acceptable transfer price is shown below:-
If the division of the transferor does not have spare capacity, the minimum transfer price is equal to variable cost per unit and the contribution margin per unit
Minimum transfer price = Variable cost per unit + (Selling price to outside customers - Variable cost per unit)
= $72 + ($120 - $72)
= $72 + $48
= $120 per unit
Therefore for computing the minimum transfer price we simply applied the above formula.
Answer:
A. $45,950
B. $0.84 per liter.
Explanation:
A. February conversion costs in the Filtration Department:
= Direct labor costs(Wages of workers operating filtration equipment) + Manufacturing overhead allocated to filtration
= $25,950 + $20,000
= $45,950
B. Filtration Department completely processed 150,000 liters in February.
Total cost incurred:
= Direct labor costs + Manufacturing overhead allocated to filtration + Water
= $25,950 + $20,000 + $80,000
= $125,950
Filtration cost per liter:
= Total cost incurred ÷ Total units processed
= $125,950 ÷ 150,000
= $0.84 per liter.