Money supply = Currency in circulation + Checkable deposits.=600 + 900 = 1500 Billion
Current deposit ratio = Currency in Circulation/ Checkable deposits. = 600/900 = .667
Excessive reserve ratio = Excess Reserves/Checkable deposits.= 15/900 = .0167
Money multiplier = (1 + C)/(rr + ER + C)= (1 + .667)/ (.0278 + .0167 + .667) = 2.343
Answer:
E. as current assets
Explanation:
As we know that the
Balance sheet records the total assets, total liabilities and the stockholder equity
Where
The total assets comprises of current assets, tangible assets, and the intangible assets
And, the total liabilities comprises of current liabilities and the long term liabilities
In the given scenario, the purchase of the newest Dorothy Cannell book be listed on the store's balance sheet. So here, the newest Dorothy Cannel book represent the current asset side of the balance sheet
False.
This is a periodic tenancy because Tom, as the tenant, may rent the apartment for successive periods under his lease, despite being "month-to-month." A tenancy at will, however, allows either the landlord or the tenant to terminate the arrangement at any time because there is more flexibility in the arrangement.
One key difference is the issue of the tenant's notice to vacate the apartment. Under periodic tenancy, the law typically requires the tenant to give at least one period (here, one month) notice to the landlord of the tenant's wish to leave the property. No such notice requirement is typically found within a tenancy at will.
Answer:
Two activities scheduled to be carried out in parallel and using the same scarce resource are independent.
Explanation:
An Israeli physicist named, Eliyahu M. Goldratt developed the Critical Chain Project Management (CCPM) and introduced it in his book "Critical Chain" in 1997.
The CCPM is a project management methodology used by managers to better manage a project. The CCPM ensures that the project plan is feasible and immune from any uncertainty or statistical fluctuations.
In the CCPM activity network, there are no milestones and all non-critical activities are performed as late as possible.
CCPM adopts the use of drum buffers, so as to ensure extra safety is applied to a project immediately before using constrained resource.
According to Goldratt, two activities scheduled to be carried out in parallel and using the same scarce resource are independent.