Answer:
Option C) 146.5
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 130 weeks
Standard Deviation, σ = 10 weeks
We are given that the distribution of completion time is a bell shaped distribution that is a normal distribution.
Formula:

P(X<x) = 0.95
We have to find the value of x such that the probability is 0.95
P(X < x)
Calculation the value from standard normal z table, we have,

The project should be completed in 146.5 weeks or less.
Hence, 146.5 weeks should be set the due date such that there is a 95 percent chance that the project will be finished by this time.
Answer:

is the answer it's was helpful to you
Answer:
The answer is >
Step-by-step explanation:
Answer:
284
Step-by-step explanation:
You have to start out multiplying the (parentheses), then the [brackets], then the {curly brackets}. After you're done with those you would add 2.
The answer is $3.21.
To find the answer, divide the total cost by the number of sq ft to get the price per sq ft.