Answer:
A. $163,800
B. $158,400
$5,400 F
C.$7,200 U
D.$12,600 F
Explanation:
A. Calculation to Determine the flexible budget materials cost for the completion of the 5,200 pairs of glasses.
Flexible budget materials cost for the completion of the 5,200 pairs
= 5200 pairs * 2 ounces * $15.75
= $163,800
b. Calculation to determine the actual materials cost incurred for the completion of the 5,200 pairs of glasses
Actual materials cost incurred for the completion of the 5,200 pairs.
= Actual material used * Actual rate
= 9,600 ounces * $16.50
= $158,400
Computation for the total materials variance
Total Material Variance = Flexible budget material cost for actual production - Actual material cost
= $163,800-$158,400
= $5,400 F
c). Calculation to determine How much of the total variance was related to the price paid to purchase the materials
Total variance was related to the price paid to purchase the materials.
Material price variance = (Standard price - Actual price) * Actual quantity
= ($15.75 - $16.50) * 9600 ounces
= $7,200 U
d) Calculation to determine How much of the difference between the answers to requirements (a) and (b) was related to the quantity of materials used
Material quantity variance = (Standard qty for actual production - Actual quantity ) * Standard rate
= (5200 * 2 ounces - 9600 ounces) * $15.75
= (10400 ounces - 9600 ounces) * $15.75
= $12,600 F