Answer:
It is important to screen your business idea because with screening it it can give you a wide variety of what's wrong with your idea and what you can do to solve it
Answer:
The average job lateness for the sequence developed is 328 days
Explanation:
Given that the initial work day is base on day 275, the following is going to be the new sequence of the given jobs:
Job Due Date
A 318 5
B 317 3
C 320 8
D 327 16
E 364 40
Therefore, the average job lateness is calculated as follows:
(318+317+320+327+364)/5=328 Days
Answer:
13.48%
Explanation:
Calculation for the required return for the company's stock using this formula
Required return = (D1/P0) +g
Let plug in the formula
Required return = [$1.12(1 + 0.115) / $62.91] + 0.115
Required return= [$1.12(1.115) / $62.91] + 0.115
Required return =(1.2488/$62.91)+0.115
Required return=0.019850580194+0.115
Required return = 0.1348 *100
Required return =13.48%
Therefore the required return for the company's stock will be 13.48