Answer:
Parson would recognize an interest revenue of $1375
Explanation:
The quoted interest rate on bond is the annual rate of interest. The bond is for 3 months which means that the interest revenue will be recorded for the 3 months period from June to August and the bond will mature on 31 August.
The interest revenue to be be recorded on this note is,
Interest Revenue = 55000 * 0.1 * 3/12 = $1375
The entry to record the receipt of interest and face value will be,
Cash 56375
Interest revenue 1375
Bonds Receivable 55000
Answer:
who knows??
Explanation:
bla bla bla ballalalallalalallalalal
The short-run average total cost of Ike's Bikes of producing 100 bikes is $360.
<h3>
What is the short-run average total cost ?</h3>
The short-run is a production period where some of the factors used in the production process are fixed and others are variable. The short-run average total cost is the total cost divided by total output. Total cost is the sum of fixed cost and variable cost.
Please find attached the complete question. To learn more about average cost, please check: brainly.com/question/26959638
Answer: $83
Explanation:
Given that,
On 1 June,
Materials purchased = 50 units
Unit price of material = $1.30
On June 15,
Materials purchased = 50 units
Unit price of material = $1.20
Total cost of 65 units:
= (Material purchased on 1 June × Unit price of material) + [(65 units - 50 units) × $1.20]
= (50 units × $1.30) + (15 units × $1.20)
= $65 + $18
= $83
The answer for Equivalent units for the period will be calculated as follows under FIFO
1. Units from beginning work in process: calculate this as beginning work in process units x (100% – given % complete) to calculate the amount of additional work needed to make the unit 100% complete.2. Units in progress and completed this period: take the units x 100% complete since they were started and completed they have received all of their materials, labor and overhead and will not receive any more since they are finished.3. Units in Ending work in process: take the ending work in process units x a given % complete.
Solution by step:
Equivalent units = 1. (5,000 × 40%) +2. (31,000 – 5,000) (Since there is a beginning work in process deduct this from the units completed) +3. (2,000 × 80%)
= 2000 + 26000 + 1600
Answer = 29,600 units