Answer:
1)
cost of making (14000*22) = 308000
cost of buying (14000*(18+6)) = 336000
Difference cost = 28000
2)
No, Since, there is not other use of fixed cost, therefore, fixed cost will be a part of cost of buying.
3-a)
cost of making (14000*22) = 308000
cost of buying (14000*18) = 252000
3-b)
Yes, Since, there is other use of fixed cost, therefore, fixed cost will not be a part of cost of buying.
Answer:
production schedule for July = 815 10-inch skillets
Explanation:
price of 10-inch skillet $28
projected sales 625 units
costs:
- direct materials $6
- direct labor $3
- manufacturing overhead $5
- sales and administrative expenses $1,000
beginning inventory 60 units
ending inventory 40% of August sales
production during July = (projected sales - beginning inventory) + (40% x projected sales August) = (625 units - 60 units) + (40% x 625 units) = 565 units + 250 units = 815 10-inch skillets
Answer:
3,500 pounds
Explanation:
By applying the below formula we get:
AQ(AP-SP)
USD 5,250 (unfavorable price variance
)
USD 5,250/(AP - SP) = AQ
So,
USD 5,250/(USD 56.50 - USD 55.00)
= 3,500
Answer:
Predetermined manufacturing overhead rate= $50 per machine-hour
Explanation:
Giving the following information:
Estimated overhead costs= $3,400,000 for indirect labor
Estimated overhead costs= $850,000 for factory utilities.
85,000 machine hours are planned for this next year
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= (3,400,000 + 850,000) / 85,000
Predetermined manufacturing overhead rate= $50 per machine-hour