Answer:
Click on the Project Tab then the Change Working Time Tab
Explanation:
The software here is believed to a MICROSOFT PROJECT. This is used often by project managers to manage projects particularly in terms of project duration, methods of the undertaking, resource management, reports, etc.
Hence, to adapt the software to this new schedule to a 7-day work week from the traditional 5-day, one should "Click on the Project Tab then the Change Working Time Tab."
This can be done by
1. Click on the Project tab, then click on Properties group
2. Click on Change working time
2. From the Change Working Time window click on "Create new calendar"
3. Name your calendar a name, in this case, "7 day week, " from there on keep following the prompt questions to finish the settings.
4. After the working times are set, click Ok.