Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Answer: 880
Explanation: 132/0.15 = 880 sry it wasnt thorough explanation i dont have time
Answer: B. The rate is 2, the initial value is 4, and the specific value is 6.
Step-by-step explanation:
for a linear function y = a*x + b
Rate = coefficient that is multiplicating the variable. ( a in this case)
Initial value = value taken of y, when we have x = 0 (b in this case)
Specific value = value forced on y.
In this case, we have:
y = 6 = 2*x + 4
Then:
The coefficient multiplicating x is 2, so the rate is 2.
The constant term is 4, so the initial value is 4.
The value equal to y is 6, so the specific value is 6.
The correct option is B.
Answer:
The answer is -1 / 6
Step-by-step explanation:
use the formula y2 - y1 / x2 - x1 = m
7 - 8 / 10 - 4 = -1 / 6
Answer:
3−y
2. 8
4.2bh
Step-by-step explanation:
5(2x+y)=15
2 Divide both sides by 55.
2x+y=\frac{15}{5}2x+y=
5
15
3 Simplify \frac{15}{5}
5
15
to 33.
2x+y=32x+y=3
4 Subtract yy from both sides.
2x=3-y2x=3−y
5 Divide both sides by 22.
x=\frac{3-y}{2}x=
2
1. 3−y
2. 8
2.Add 2y2y to both sides.
x=-8+2yx=−8+2y
2 Regroup terms.
x=2y-8x=2y−8