Answer:
D) Project importance is enhanced by setting authority equal to that of functional departments.
Explanation:
A matrix organization is characterized by, multiple command system and overlapping of command, control and behavioral pattern.
Here, temporary project groups are created so as to handle short term projects. Personnel are drawn from functional department and their activities are controlled and coordinated by a project manager.
Once a project is completed, the structure is disbanded and the personnel return to their original departments i.e functional department.
During the project duration, a person is responsible and reports to two bosses, one being the project manager and secondly to the functional boss. Thus, under such a structure exists dual reporting.
Under matrix structure for project management, the project manager is not allowed to use resources exclusively for the project i.e like in project management. Rather, such a manager is required to share resources with the organization.
Answer:
Idk if this is the right answer but I Google it and I got virtual reality/artificial intelligence and autonomous vehicles
Answer:
$80,160.
Explanation:
An account receivable is lawfully enforceable cases for installment, held by a business for the products provided and benefits that clients/customers have requested yet not paid for.
According to Rahal's autos noncollectable accounts and the amount they received in the following year. Rahal's collectible accounts on December 31, 2021, is
86,500 + 404,000 - 408,000 - 2,340
Answer:
Option C because it is impossible to determine the legality based on the facts given.
Explanation: