Answer:
Formatting text is how something is specifically layed out. Specific style.
Explanation:
The correct answer to this open question is the following.
Although there are no options attached we can say the following.
Do earthquakes ever happen in Malaysia?
Yes, they do. And they are very frequent and high in intensity.
For instance, the Sabah earthquake in 2015.
On June 5, 2015, the region of Malaysia was hit by a strong earthquake, 6.0 of magnitude on the Ritcher scale. The telluric movement lasted 30 seconds and caused much destruction.
Experts and scientists confirm that this had been the strongest earthquake since the one presented in 1976.
The type of service offers a preconfigured testing environment for application developers to create new software applications is Software as a Service (SaaS).
<h3>What is software as a service SaaS?</h3>
Software as a service (SaaS) is known to be a type of service that gives its users the ability to be able to link to and also use cloud-based apps in course of the Internet.
Conclusively, The type of service offers a preconfigured testing environment for application developers to create new software applications is Software as a Service (SaaS) as it gives its best service.
Learn more about application developers from
brainly.com/question/11352260
#SPJ1
Answer:
The correct answer is C) With respect to PERT and CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.
Explanation:
The CPM (Critical Path Method) method is frequently used in the development and control of projects whose tasks have a fixed duration while the PERT (Program Evaluation and Review Techniques) method is a set of techniques with the same purpose but that allows to work with tasks with estimated probability duration but not deterministic.
Both methods are based on developing a complete scheme that includes all the tasks of a project linked to each other according to their sequence, determining the duration and analyzing different ways of reconfiguring the task planning to optimize the use of the resources of according to the general objectives of the project.
There are tasks that to start performing them must have been completed one or more previous tasks. The overall duration of the project is determined by the Critical Path, which is the sequence of tasks of greater duration. The tasks belonging to the critical path have to be carried out with special care because delays in them would cause delays in the total achievement of the project. That is why these tasks have no slack.
The rest of the tasks have some slack, which is determined by the time that a previous task can be delayed without delaying the total time of completion of the project, that is, not exceeding the duration determined by the critical path.
That is that why we say that the <em>slack</em><em> is the amount of time a task may be delayed without changing the overall project completion time</em>.