Answer:
There are multiple critical paths
Explanation:
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.
The essential technique for using CPM is to construct a model of the project that includes the following:
- A list of all activities required to complete the project (typically categorized within a work breakdown structure),
- The time (duration) that each activity will take to complete,
- The dependencies between the activities and,
- Logical end points such as milestones or deliverable items.
Using these values, CPM calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer).
considering the above function of the cpm analysis because you have multiple path, there is tendency that more than path through the project network will have zero slack values.
Answer:
In C++:
#include <bits/stdc++.h>
#include <iostream>
#include <vector>
using namespace std;
int main(){
vector<int> vectItems;
cout << "Vector length: ";
int ln; cin>>ln;
int num;
for (int ikk = 0; ikk < ln; ikk++){
cin >> num;
vectItems.push_back(num);}
int small, secsmall;
small = secsmall = INT_MAX;
for (int ikk = 0; ikk < ln; ikk++){
if(vectItems[ikk] < small){
secsmall = small;
small = vectItems[ikk]; }
else if (vectItems[ikk] < secsmall && vectItems[ikk] != small) {
secsmall = vectItems[ikk];} }
cout<<small<<" "<<secsmall;
return 0;}
Explanation:
See attachment for program file where comments are used for explanation
Answer:
All of the above is the correct answer to the given question .
Explanation:
As the Ken olson is the Ken Olson, president of the Digital Equipment Organization . Following are the predictions of Ken olson of the the technology that are wrong.
- Lack of creativity regarding the current applications that the user has would consider for the technology.
- Lack of creativity regarding the user or the client has liking.
- Lack of creativity on what the government would be charging ford. Any of these
So we will choose the Option all these.
Answer:
Network diagrams.
Explanation:
In this scenario, Jason is the network manager and is leading a project to deploy a storage area network (SAN). He is working with the vendor's support technician to properly set up and configure the SAN on the network. To begin SAN input and output (I/O) optimization, Jason need to provide the network diagram to the vendor support technician.
A network diagram can be defined as a graphical representation of the topology of a network connection.
Basically, it gives an illustration of all the equipments such as routers, switches, hubs etc.