Answer:
11
Step-by-step explanation:
Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
-15
Step-by-step explanation:
start from the inside and go out.
So first plug in -3 into g(x)
g(-3) = -3 - 7 = -10
then plug in -10 into f(x)
f(-10) = 2(-10) + 5 = -15
so f(g(x)) = -15
48 feet
Divide 858 by 18 to get 47.6 > simplify > 48 feet
The graph represents a function but the table does not. The reason for this is that one input value (70) in the table is associated with two output values (54.6 and 53.11), which is a sure sign that we do NOT have a function here.