Answer:
In total it capitalized <em>84,180.82 dollars</em>
<em />
Explanation:
construction capitalized interest
date expenditures weight
01-jul 680,000.00 0.75 508,602.74
30-sep 1,020,000.00 0.50 508,602.74
30-sep 1,020,000.00 0.50 508,602.74
30-ene 960,000.00 0.16 <u> 157,808.22 </u>
TOTAL 1,683,616.44
average rate
principal rate interest
2,000,000 0.09 180000
8,000,000 0.04 320000
10,000,000 500000
total interest / total principal = 0.05
<u>Capitalized interest:</u>
1,683,616.44 x 0.05 = <em>84,180.82 </em>