1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
zaharov [31]
2 years ago
14

Het opt-shirt made of 50 cotton 50polyester so what does percent mean ​

Mathematics
2 answers:
Anuta_ua [19.1K]2 years ago
6 0
50% cotton 50% polyester
solniwko [45]2 years ago
3 0
It means that shirt is made of 50% cotton and 50% polyester aka 50/50 cottonpoly blend
You might be interested in
What are the solutions of the equation 6x2 +5x+1 = 0 ?
STatiana [176]

Answer:

Step-by-step explanation:

6x^2+5x+1=0

Descr= b^2-4ac

Descr= 25-24=1

X1= (-b+√descr)/2a = (-5+1)/12= -1/3

X2= (-b-√descr)/2a = (-5-1)/12= -1/2

6 0
3 years ago
Read 2 more answers
4. The population of a town is modeled by the equation P - 165812002, where "p"
Pavel [41]
Is that all the information ? I think they’re missing something
5 0
3 years ago
An entertainment firm offers several DJ choices and light shows that range in price based on the rental time period. The DJ's co
snow_tiger [21]
From $378 (min) to $528 (max) per night
3 0
3 years ago
Read 2 more answers
PLEASE HELP ASAD
irinina [24]

Answer:

Multiply g by 23 to get

the missing value in the last row is 92.

A real-world situation that is represented in the table is “Rio’s car gets 23 miles per gallon.”.

or A,D,E

6 0
2 years ago
Read 2 more answers
A and B working together can do a work in 6 days. If A takes 5 days less than B to finish the work, in how many days B alone can
svetlana [45]

Answer:

15 days

Step-by-step explanation:

Let x be the number of days needed for B to complete the job. Then x-5 is the number of days needed for A to complete the job.

In 1 day,

  • A completes \dfrac{1}{x-5} of all work;
  • B completes \dfrac{1}{x} of all work.

Hence, in 1 day both A and B complete \dfrac{1}{x-5}+\dfrac{1}{x} of all work. A and B working together can do a work in 6 days. Then

6\cdot \left(\dfrac{1}{x-5}+\dfrac{1}{x}\right)=1.

Solve this equation:

\dfrac{6x+6x-30}{x(x-5)}=1,\\ \\12x-30=x^2-5x,\\ \\x^2-17x+30=0,\\ \\D=(-17)^2-4\cdot 30=289-120=169=13^2,\\ \\x_{1,2}=\dfrac{17\pm 13}{2}=2,\ 15.

If x=2, then x-5=-3 that is impossible. So, B needs 15 days to complete the work alone.

6 0
2 years ago
Other questions:
  • What does it mean to find the point P on GK such that 3(GP)=2(PK
    10·1 answer
  • a collection of 27 coins consist of 20-cent and $2 coins, and has a value of $23.40. find the number of coins of each denominati
    14·1 answer
  • How many fourths are in two wholes? Use a fraction model to help you. Show two whole divided into four equal pieces. 2 dived by
    12·2 answers
  • Two complementary angles are in the ratio of 1:5. find the measure of the larger angle?
    9·1 answer
  • Find the total cost to the nearest cent. $15 lunch; 20% tip.
    15·1 answer
  • which of the following sets of numbers will form a right triangle A. 12,13,14 B. 15,16,18 C. 5,6,9 D.5,12,13
    15·1 answer
  • Solve for x in the equation x^2 + 4x - 4 = 8
    8·2 answers
  • Hey can u help with the following questions because I don't get this.
    14·1 answer
  • Name the kind or kinds of symmetry the following figure has: point, line, plane, or none. (Select all that apply.)
    6·1 answer
  • Madelyn takes 8 quizzes each week. Is the total number of quizzes Madelyn takes
    12·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!