Answer: (C) Competitive intelligence
Explanation:
The competitive intelligence is one of the process of analyzing the various types of information that helps in learned abut the market, consumers and the competitors.
The main objective of the competitive intelligence is that it helps in support the various types of strategic decisions in an organization.
According to the given question, the competitive intelligence is helps in gathering the data for improving the ability of an organization in this competitive environment.
Therefore, Option (C) is correct answer.
Answer:
correct answer is 4) $169,000.00
Explanation:
given data
received distributions totaling = $14,000
remaining benefits lump-sum = $155,000
solution
we know that substantial payment by as distribution method not subjected to the early distribution penalty
but lum sum amount distribution before age 59.5 is subject to 10% penalty
so here we can say till 59.5 year annuity payment not changed
so amount subject to the penalty is = $14000 + $155000
amount subject to the penalty is = $169000
so correct answer is 4) $169,000.00
Answer:
c.long-range time horizon.
Explanation:
Forecasts consider long-range time horizon to improve accuracy and provide more authenticity.
Answer: 4,975 units
Explanation:
Budgeted production in July = Sales forecast for July + Ending inventory for July - Beginning inventory
Beginning inventory = 25% of July sales
= 25% * 4,800
= 1,200 units
Ending inventory = 25% of August sales
= 25% * 5,500
= 1,375 units
Budgeted production is therefore:
= 4,800 + 1,375 - 1,200
= 4,975 units
Answer:
b) internal rate of return will exceed its required rate of return.
Explanation:
The internal rate of return is the discount rate at which the NPV = 0. If the NPV is positive when calculated using the project's discount rate, then the IRR is going to be higher than the discount rate.
Option A is wrong because the profitability index (PI) of a project is calculated by dividing the present value of its cash flows by its cost. If the NPV is positive, it means that the present value of its cash flows will be greater than the costs, so the pI will be more than 1.
Option C is wrong because if the costs exceed the benefits, then the NPV will be negative.
Option D is wrong because that would mean that the NPV is negative.
Option E is something made up that doesn't make any sense.