Answer:
There are 96 boys in the soccer league.
Step-by-step explanation:
You multiply 160 by 60%, which is also 160*.6.
160*.6=96
56 oz
shshnsnsnsjizjxbhxusj
Answer:
<em>Solution: (26,15)
</em>
<em>
</em>
<em>Cars washed=26
</em>
<em>
</em>
<em>Trucks washed=15</em>
Step-by-step explanation:
Answer:
x = 42.5
Step-by-step explanation:
It is said:
If two angles are not corresponding, then they make up 180°. They are more known as supplementary angles.
So the equation is:
a + b = 180°
Substitute
x + 8 + 3 x + 2 = 180°
x + 3x + 8 + 2 = 180°
4x + 10° = 180°
4x = 180° - 10°
4x = 170°
x = 170° ÷ 4
x = 42.5
Answer:
<em>Most likely time, </em>according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
- An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
- A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
- A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
- An <em>expected time</em>, an statistical estimation.
Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":
- "[...] in as few as 15 days" is the <em>optimistic time</em>.
- "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
- "[...] but most likely will require 20 days" is the <em>most likely time</em>.
As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.