1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
daser333 [38]
3 years ago
7

Factorise x^2 + 5x + 6= 0

Mathematics
1 answer:
musickatia [10]3 years ago
8 0

Answer:

(x +2) (x+3) = 0  

x = -2  x = -3

Step-by-step explanation:

x^2 + 5x+ 6 = 0

To remember how to factor

key word remember word .......d. a. t. p, c

distribute x,  add two no's, that also multiply, put together, change sign see below.

step 1  distribute square brackets that mean x^2   =  (x   )  (x  )

step 2 add two numbers that add to get 5

step 3  that also multiply to get 6                            =   (+2) (+3) = 0

step 4  put together                                                  = (x +2) (x+3) = 0    

step 5  change sign to = x                                        =  x = -2  x = -3

You might be interested in
HELP <br><br>MMEEE!! i will give brainly
LUCKY_DIMON [66]

Answer:

the answer is 28 in

hope this helps

8 0
2 years ago
Read 2 more answers
Write your own example of a biased question. I need this ASAP. Pls
Anna35 [415]

Answer:

it is like a question so do you like orange or red better is a baised question

Step-by-step explanation:

hope this helped!!!!

4 0
2 years ago
Read 2 more answers
Divide 2x^3+4x^2+5 by x-3 using long division.
Pepsi [2]

Answer:

2x^2 + 10x + 30 + 95/x-3

Step-by-step explanation:

Hope this helps!

5 0
3 years ago
Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the time to correct the problem
jasenka [17]

Answer:

The risk consequence of both activities is 1.6 months.

Step-by-step explanation:

We can define a randome variable D: total delay time for the project, and calculate its expected value.

This would be the risk consequence of both activities.

The expected delay time for the project is the sum of the expected delay for task A plus the expected delay for task B. It is assumed the likelihood of a problem in any task is independent of the other.

Then, each expected delay for a task is equal to the probability of a problem multiplied by the consequence (delay time).

E(D)=E(D_a)+E(D_b)=p_aT_a+p_bT_b\\\\E(D)=0.5*2+0.2*3=1+0.6=1.6

The risk consequence of both activities is 1.6 months.

6 0
3 years ago
Graph the image of this figure after a dilation with a scale factor of 12centered at the origin.
makvit [3.9K]

Answer:

1.(-4,2)

2.(2,4)

3.(-2,8)

4 0
2 years ago
Other questions:
  • Suppose you have 7 dark chocolates and 9 light chocolates in a box.
    7·1 answer
  • What is the volume of a baseball with a diameter of 56 mm
    14·1 answer
  • the stopping distance of an automobile is directly proportional to the square of its speed v. a car required 90 feet to stop whe
    8·1 answer
  • What is scale factor ?
    8·2 answers
  • An architect finds some unlabeled dimensions on a blueprint, and no scale is shown. A 14-foot wall that has already been built m
    15·2 answers
  • Holly plans to attend community college next year her expenses are only $1,200 because her parents are paying the rest holly ear
    5·2 answers
  • A cone fits inside a square pyramid as shown. For every cross section, the ratio of the area of the circle to the area of the sq
    13·2 answers
  • I need help with part B.
    7·1 answer
  • Name the angles.......
    11·1 answer
  • 4. consider the equation, x6 −2x5 3x2 −2. according to the fundamental theorem of algebra, how many complex solutions does this
    8·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!