Answer:
See below.
Step-by-step explanation:
Time taken by (A+B) to finish the work = 12 days
Time Taken by (B+C) to finish the work = 15 days
Time taken by (C+A) to finish the work = 20 days
Therefore,2 ( A + B + C)'s 1 day's work-
Therefore, A, B and C together can finish the work in 10 days.
Now,
A's 1 day's work = (A+B+C)'s 1 day's work - (B+C)'s 1 day's work
- Hence,A alone can finish the work in 30 days.
B's 1 day's work = (A+B+C)'s 1 day's work - (A+C')s 1 day's work
- Hence,B alone can finish the work in 20 days.