Answer:
safety stock = 33 desks
reorder point = 133 desks
Explanation:
safety stock = (Z-score x √lead time x standard deviation of demand) + (Z-score x standard deviation of lead time x average demand)
- Z-score for 98% confidence level = 2.326
- standard deviation of demand = 10
- √lead time = √2 = 1.414
- we are not given any standard deviation of lead time, so we can assume that it is 0
safety stock = (2.326 x 1.414 x 10) + (2.326 x 0 x 50) = 32.89 ≈ 33 desks
reorder point = lead time demand + safety stock = (50 x 2) + 33 = 133
Answer:
Following journal entries would be recorded:
Cash A/C Dr. $144000
To Common Stock (4800 shares × 10) 48000
To Paid in capital A/C (4800 shares × 20) 96000
(Being issue of common stock recorded)
Treasury Stock A/C (470 × 25) Dr. 11750
To Cash A/C 11750
(Being purchase of 470 shares recorded)
Cash A/c (470 shares × 30) Dr 14100
To Treasury Stock A/C (470 × 25) 11750
To Paid in capital from treasury stock 2350
(Being sale of treasury stock being recorded)
I believe the answer is Asia
Knowledge management refers to the process of achieving company's goal by Using the best use of a certain knowledge.
Business owners that derived from Asian culture, tend to favor this ability rather than warm connection that favored by western business owners
Answer:
3000
1500
Explanation:
For each of the answers in this question I have added the formulas to solve them in the attachment below
1.
(45-39)*5*100
= 3000
2.
(45-39)-3 x5 x100
= $1500